RA4 Office and Manufacturing Building
This design-build BIM project included over 160,000 LF of piping, all process and wet HVAC, multiple cooling tower installations, and any associated equipment.
RA4 Office and Manufacturing Building
This design-build BIM project included over 160,000 LF of piping, all process and wet HVAC, multiple cooling tower installations, and any associated equipment.
Project Details
Location
Hillsboro, OR
Contract Value
$75 Million
GC
Balfour Beatty
Market
Advanced Technology - Semiconductor
Completed In
2015
Project Summary
Leading the Way in Lean Construction
RA4 is a seven-story, 950,000 SF office and manufacturing building for the world’s leading manufacturer of microchips. Harder’s scope for this design-build BIM project included all process and wet HVAC mechanical work. Harder fabricated and installed 36” CWP, 24” HWP, 12” OFA, and 10” AWN and HFW, totaling over 160,000 LF of piping.
The corridor carts designed by Harder were an excellent example of off-site pre-fabrication. Pre-fabricated pipe was loaded in sequence of installation on wheeled carts designed to be lifted so nothing hit the ground. With conditions being extremely congested and zero lay-down area available, we had to optimize all opportunities to move pre-fabrication work off-site for consolidated deliveries.
The spirit of cooperation and collaboration was a major reason why this successful project was highlighted at the annual Lean Congress in San Francisco, CA.
160,000 LF
of piping installed in facility
Services Used
Related Projects
The Owner brought Harder onboard to expand the fab’s general exhaust system so it could support a new tool set and to consolidate several smaller standalone general exhaust systems into one.