Harder designed the new mechanical system using owner-provided equipment including stills, condensers, tanks, and conveying lines.
Project Breakdown
Budget
$1.4
Million
Location
Portland
OR
Project Summary
Tight Spaces, Tight Schedule, Great Success
Harder Mechanical fabricated and installed all clean-in-place (CIP) process piping and steam lines, set and hooked up all tanks and equipment including two 3,170-gallon distillation tanks, and installed all bottling line and conveying equipment. All mechanical work was designed around owner-provided equipment.
This project was a challenge due to the tight work area setting the equipment, with some of the tanks standing at 30 feet tall. Our team hit all schedule dates and provided many custom parts to convert from metric tube systems to a standard sanitary tube system.
No two projects are ever the same. At Harder, we approach each project individually, tailoring our approach to meet the needs of our client. But we bring our past experiences to the table to make sure we are always providing the best-in-class service our clients expect.