Harder designed the new mechanical system using owner-provided equipment including stills, condensers, tanks, and conveying lines.

Aviation Gin Distillery

Harder designed the new mechanical system using owner-provided equipment including stills, condensers, tanks, and conveying lines.

Project Details

Location
Portland, OR
Contract Value
$1.4 Million
GC
R&H Construction
Market
Commercial - Food & Beverage
Completed In
2021

Project Summary

Tight Spaces, Tight Schedule, Great Success

Harder Mechanical fabricated and installed all clean-in-place (CIP) process piping and steam lines, set and hooked up all tanks and equipment including two 3,170-gallon distillation tanks, and installed all bottling line and conveying equipment. All mechanical work was designed around owner-provided equipment.

This project was a challenge due to the tight work area setting the equipment, with some of the tanks standing at 30 feet tall. Our team hit all schedule dates and provided many custom parts to convert from metric tube systems to a standard sanitary tube system.

3,170 gallons

Capacity of each of the two distillation tanks

Services Used

  • Design Services

  • Equipment Installation

  • Fabrication

  • Plumbing

  • Process Piping

  • Tank Installation & Modification

  • Virtual Design & Construction

Related Projects

Your Project is Next

We’re ready to bring this expertise to your upcoming project. Contact us today to get started.

Your Project is Next

We’re ready to bring this expertise to your upcoming project. Contact us today to get started.